Two more segments of the City’s Connecting Link have been approved for reconstruction. Council has awarded the contract for segments 9 and 10, Brunette Rd. to Father Costello Dr. E., to GIP Interpaving Ltd. in the amount of $17,960,701.85 + HST. Due to the scope and complexity of the project, construction will be carried out over two years.
Work will begin this year on Segment 9, stretching approximately 700 metres from Brunette Rd. to Hwy. 655. Motorists will agree that this section is priority due to deteriorating asphalt. Full road surface reconstruction is planned, including new asphalt, curbs, sidewalks, and traffic medians. Sections of watermain and storm sewer infrastructure will be replaced, along with the traffic signals at Brunette Rd. and Hwy. 655, and streetlights will be upgraded to meet current standards.
Construction will require lane reductions only with phased traffic control. Access to all businesses and properties will be maintained throughout the project. The City has spoken directly to business and property owners in Segment 9 and will continue to provide timely updates.
“We are also working closely with Cochrane District Paramedic Service,” adds Scott Tam, Director of Growth and Infrastructure. “Emergency service operations, including ambulance access, will remain uninterrupted during construction.”
GIP Interpaving Ltd. will also complete Segment 13 of the Connecting Link this year. An updated construction timeline is expected in the coming weeks. While an exact start date for Segment 9 has not been confirmed, the City will provide updates as they become available.
For more information on rehabilitation of the City’s Connecting Link, visit: https://www.timmins.ca/our_services/engineering/connecting_links.
|