Reconstruction of William Ave. Phase 2

Reconstruction of William Ave. Phase 2

William Ave

Project Details:

The full reconstruction of William Ave. from Main St. to Crawford St. and Front St. to Huot St. will be completed in two phases. The construction of Phase 1 will include the replacement of the watermain, sanitary sewer, and storm sewer. Phase 1 will be completed in 2018 with new 1.5m sidewalk for the North side of William Ave. The construction of Phase 2 will be scheduled for 2019 and it will include regrade of the 9m roadway and 1.5m gutter banks, property restoration, and asphalt the roadway and gutter banks.

Property Location: William Ave. (Main St. to Crawford St.) & (Front St. to Huot St.)

Tender Value: $951,876.70

Contractor: Caron Equipment Inc.

Completion: June 30, 2019

Status: Reconstruction - Phase 2

City Staff:

Project Manager: Christina Millions

On-Site Inspector: Cory Falardeau

Email: [email protected]

Phone: (705)360-2600 ext. 4856